CONSTRUCTION OF ROADS, DRAINS AND CULVERTS AT FOUR MILES BARTICA
![BARTICA](https://static.wixstatic.com/media/b956ad_ed88d9b82beb4f15ab0442b30c01610c~mv2.png/v1/fill/w_750,h_424,al_c,q_85,usm_0.66_1.00_0.01,enc_avif,quality_auto/Image-empty-state.png)
The contract for this project was signed on September 13, 2004 by the Government of Guyana, Ministry of Housing and Water and the Contractor, B&J Civil Works for a sum of G$114,891,634. The scope of works for this project include the construction of approximately 2.5 miles of main and secondary roads. The original road-works design comprised of 11”laterite base course and a Double Bituminous Surface Treatment final layer. The initial road widths were 12 and 16 ft, however six of the 12 ft roads have been widened to 14 ft. T